WXOW.comreportedon Didion Milling CEO John Didion who met with Cambria, WI, village board to discuss the future plans of the company. On May 31 Didion Milling experienced an explosion that ended up killing five people and severely damaging the plant. The company plans on tearing down and rebuilding the plant with state-of-the-art equipment. The demolition of the old mill will begin July 10,and the ethanol plant that is also on site will be full back on line once the demolition is complete. Didion Milling is currently working on finding jobs for all of the employees who used to work at the plant, and has reported that grain operations will not be affected.
Didion Milling to Rebuild
Demolition will start July 10
November 30, 2020